Campus relocation or a school merger isn’t only about classrooms and furniture — interactive whiteboards, indoor LED displays, audio and campus live-streaming systems are precision equipment that is often left until the last minute, leaving new campuses without working displays on day one.
8 things to plan before you move:
1. Early equipment inventory
Start 3–6 months out: every touchscreen’s room/model/size/mount, LED display specs and mounting, TV counts, audio inventory, streaming encoders/cameras, cabinets and cabling. Photograph and log every item — tendering, transport and reinstallation all depend on this list.
2. Moving vs engineering are different trades
Movers handle furniture; LED modules, touchscreens and audio racks need numbered dismantling, shock-proof/anti-static packing, crating, and post-install calibration (touch, pixel-by-pixel LED, audio EQ). Use an engineering contractor for the technical dismantle-and-reinstall.
3. Structural assessment for large LED walls
A large indoor LED display (e.g., hall main screen) needs RPE structural assessment and safety certification in line with EMSD requirements — schedule this early in the relocation programme.
4. Cabling during the fit-out window
- HDMI 2.1 + USB touch extensions per classroom (extension solutions when the host is beyond one cable run)
- ≥50 mm power/signal separation or shielded conduit
- Fire-retardant audio trunking
- Pre-run lines for hall audio and streaming positions
Retrofitting cables after fit-out means surface trunking — ugly and slow.
5. Allow lead time for tendering
Start tender packs 4–6 months ahead; specify dismantle lists, packing/transport method, structural assessment, cabling drawings, programme and acceptance tests; mind quotation validity and approval cycles.
6. Back-schedule from opening day
- T-8 to T-12 weeks: award tender, detailed design
- T-4 weeks: dismantle, number, pack
- T-2 to T-3 weeks: transport, reinstall, cabling
- T-1 week: touch/LED calibration, audio tuning, stream tests, integrated acceptance
- T-0: completion documents, safety certificates, staff briefing
Summer is peak season — book engineers early.
7. Acceptance checklist, not “it turns on”
- Per-board touch tests: no drift, audio-video sync
- LED: pixel-by-pixel calibration, no dead pixels, even brightness
- TVs: multi-screen sync
- Audio: zone levels, wireless mics, no feedback
- Streaming: in/out-campus tests pass
- Documents: safety certificates, as-built drawings, equipment list, warranty terms
8. People need handover too
Arrange staff briefing on boards/audio/streaming, support contacts, and a basic fault-finding guide.
Common mistakes we see on site
- ❌ Movers only — no one to reinstall or calibrate
- ❌ LED walls mounted without structural assessment
- ❌ Cabling considered after fit-out
- ❌ Tendering too late for the summer window
- ❌ Acceptance signed without a checklist
VDiGi has years of school-sector IT and AV engineering experience, including the recent campus-merger equipment relocation for Ng Wah Catholic Primary School. Planning a relocation or merger? Contact us for a free site survey and initial advice.
Learn about our campus relocation & merger engineering service →